Ok. It was sort of a Wham! Bam! kind of morning. Abraham and his crew showed up at 7:15 AM this morning. We had gotten blocks delivered yesterday evening, but they weren't needed for this part of the project. The 35 bags of cement were promised "first thing", but since they didn't open till 8:00 AM, nothing was happening there for a while. It was a good thing we had a reserve of 9 bags stored in the well house. That and Elsie's sand and gravel saved the day and got everyone busy till deliveries could take effect.
Here's a nice shot of the "Machine". Bob's mixer works really nicely. Even with 35 bags, plus the 9 we started out with, we ran short. Abraham and I made a quick run into town to Gomez's to purchase and haul an additional 10 bags.
Here's the Streetside breezeway and the generator room pretty much done.
Pouring the Canalside breezeway. Overall, the pour went really fast.
No comments:
Post a Comment
We want to get your thoughts about our posts, and what you would like to see here.
Unfortunately, adding an image to your comment can't be done directly. The only way you can do it is to include the URL of the image from a hosing server, which means that first, you must upload your image to Flickr, Dropbox, or some other image hosting server.
Not very good, but that's all that is available right now.
To post a YouTube video, simply enter the video URL in the comment box. It will appear in the comment box ready to play.
Note: Only a member of this blog may post a comment.